Junction Landscaping

 

This project started with having to excavate and dispose 1500sq ft of concrete. During excavation we noticed there was the existing concrete surface, underneath was asphalt, and then another 4’ of concrete. It became an excavation and disposal nightmare due to it now being contaminated disposal. After excavation, the earth was levelled and left for 3 weeks to settle. In the mean time we formed and poured 4 new concrete stairs and landing entrances to the building. After 3 weeks passed, ensuring the earth settled enough, we came back to begin the installation of the new stone and complete the asphalt driveway. The job was complete in 5 days